Lancelot Lancelot

Lancellot Place

ONE MEP was instructed to design supply and install a new fire alarm system to up-grade the existing system to live occupied areas and install new to the refurbished spaces. Working closely with the facilities team to up-grade the fire alarm with minimal disruption to live occupied spaces by validating and utilising existing cabling to keep disruption and builders works to a minimum.

Site temporary services provided to the refurbishment areas to allow safe working environment and power to the construction team.

Delivery:

  • Fire alarm up-grade
  • Networked fire system

Key Features:

  • Fire system to LD1
  • Cause and Effect designed to clients bespoke requirements
  • Combined PAVA  
  • Client: Beam
  • Completion: Winter 2024
  • Project Type: Refurbishment
  • Sector: Hotel
  • Value: £133k
  • Main Contractor: Red Construction
  • Facilities Manager: In-house Maintenance Team
  • End User: Multiple Occupancy